Traffic Advisories

The eastbound ONLY detour of Mill Road in Egg Harbor Township has been postponed by the contractor due to recent storm activity that caused work delays.
The new effective date is Monday, August 3.

This eastbound detour of Mill Road between Old Zion Road (Spruce Avenue) and Fire Road will be in effect 24 hours a day and is expected to last into November as work continues on the county’s intersection improvements at Fire & Mill roads. The westbound lane will remain open.

Motorists are advised to follow the posted detour or seek an alternate route and plan travel time accordingly.

For more information about this project, including the detour route, visit http://www.aclink.org/Planning/MainPages/mill-and-fire-intersection.asp


Mill Road and Fire Road Improvement Project

The improvements at the intersection of Mill Road and Fire Road in Egg Harbor Township will significantly enhance the capacity and function of this important intersection, located within one of Atlantic County's growth areas. The presence of the Garden State Parkway and the extent of wetlands and other environmentally sensitive areas all served to limit the potential for a larger expansion of this intersection, and required extensive regulatory review under both the NJDEP and Pinelands Commission due to the joint jurisdiction held by both agencies. Extensive off site mitigation was required under the three NJDEP and the single Pinelands permit.

Public Information Session
March 5, 2014
Egg Harbor Township Hall

View Photo Gallery Camera

View News Video Video

FACT SHEET

  • Fire Road Southbound will be expanded to 4 lanes, with 2 through lanes, 1 dedicated left turn and 1 dedicated right turn.
  • Fire Road Northbound will have 1 dedicated left turn lane, 1 dedicted through lane and 1 shared through/right lane.
  • Mill Road Eastbound will have 1 dedicated right turn ramp, 1 dedicated left turn lane and 1 shared through left lane.
  • Mill Road Westbound will have 1 dedicated right turn lane and 1 shared through left lane.
  • Intersection will be video controlled, with capacity for timing and phasing revisions if required.
  • Intersection will include pedestrian crosswalks.
  • CONSTRUCTION START
    • Anticipated Construction start following bid and award is Spring, 2014.
  • CONSTRUCTION SEQUENCE
    • Construction started mid-July 2014. Utility relocations are nearing completion. On or about August 3, 2015 eastbound Mill Road will be closed through the completion of the project, anticipated to be in November 2015.  The detour for eastbound Mill Road will be south on Old Zion Road (Spruce Avenue) to eastbound Zion Road to Fire Road.  Remaining work will be completed using lane shifts.
  • LENGTH OF PROJECT: Overall length of project from start to finish is approximately 18-19 months.  Consisting of preparation work (up to 6 months) to accommodate the relocation of high power utility poles. The relocation of these poles will clear the way for the remaining construction improvements (up to 6-7 months).
  • DETOUR ROUTE: 

Striping Plan (Map of intersection)pdf

ASSOCIATED PROJECTS

Two other related transportation projects will be executed in conjunction with this project.  The replacement of the Maple Run Bridge on Mill Road in Egg Harbor Township and Northfield, and the replacement of the Cedar Bridge on Zion Road, in Egg Harbor Township, Northfield and Linwood will occur in conjunction with the Intersection Project. Each bridge is a critical alternate route within the detour plan for the other bridge and will therefore be replaced in tandem. Replacement of the Maple Run Bridge will occur first, within the construction period of the intersection.  

Sequence of construction associated with Fire/Mill Intersection, Maple Run Bridge Replacement, Cedar Bridge Replacement.

REPLACEMENT OF MAPLE RUN BRIDGE

  • CONSTRUCTION START:  March, 2014 (Concurrent with intersection project)
  • CONSTRUCTION SEQUENCE:
    • Move/Replace Utilities
    • Remove Bridge Structure, Demolish Footings
    • Replace Footings, Supports
    • Install/Construct New Bridge and Roadway Surface
    • Bridge will be demolished and replaced. Mill Road will be closed in vicinity of the bridge, as this work is underway.
  • CONSTRUCTION COMPLETION: June, 2014

REPLACEMENT OF CEDAR BRIDGE

  • CONSTRUCTION START: January, 2015
  • CONSTRUCTION SEQUENCE:
    • Move/Replace Utilities
    • Remove Bridge Structure, Demolish Footings
    • Replace Footings, Supports
    • Install/Construct New Bridge and Roadway Surface
    • Bridge will be demolished and replaced. Zion Road will be closed in vicinity of the bridge, as work is underway.
  • ANTICIPATED COMPLETION: Fall 2015
  • TRAFFIC CONTROL: Full Detour
  • DETOUR ROUTE: