Traffic Advisories

On Tuesday, July 29 and Wednesday, July 30, a lane shift/shoulder closing will be in effect in the southbound lanes of Fire Road in Egg Harbor Township during the preliminary phase of construction for the county’s improvements to the intersection of Fire and Mill roads. Motorists are advised to follow the posted detour and allow extra time for travel or to seek alternate routes.

For more information about this intersection project, visit www.aclink.org/planning.

Beginning Wednesday, July 23 through Wednesday, July 30, a lane shift traffic pattern will be in effect in the southbound lane of Fire Road at the intersection of Route 322/40 in Egg Harbor Township, 7 AM to 3:30 PM, weekdays only, for work by a private developer. Lanes in both directions will remain open to traffic.

Police will be onsite to assist. Work is contingent on weather conditions.  

Beginning Monday, July 14, a periodic detour may be utilized for eastbound traffic only on Mill Road in Egg Harbor Township, Monday through Friday, between the hours of 7 AM and 5 PM, during the preliminary phase of construction for the county’s improvements to the intersection of Fire and Mill roads.

Motorists are advised to follow the posted detour and allow extra time for travel or to seek alternate routes.

Mill Road and Fire Road Improvement Project

The improvements at the intersection of Mill Road and Fire Road in Egg Harbor Township will significantly enhance the capacity and function of this important intersection, located within one of Atlantic County's growth areas. The presence of the Garden State Parkway and the extent of wetlands and other environmentally sensitive areas all served to limit the potential for a larger expansion of this intersection, and required extensive regulatory review under both the NJDEP and Pinelands Commission due to the joint jurisdiction held by both agencies. Extensive off site mitigation was required under the three NJDEP and the single Pinelands permit.

Public Information Session
March 5, 2014
Egg Harbor Township Hall

View Photo Gallery Camera

View News Video Video

FACT SHEET

  • Fire Road Southbound will be expanded to 4 lanes, with 2 through lanes, 1 dedicated left turn and 1 dedicated right turn.
  • Fire Road Northbound will be expanded to 3 lanes including 2 through lanes, 1 dedicated left turn lane.
  • Mill Road Eastbound will be expanded to 3 lanes, with 1 through lane, 1 dedicated left turn and 1 dedicated right turn.
  • Mill Road Westbound will be expanded to 2 lanes, with 1 through lane and 1 dedicated right turn lane.
  • Intersection will be signal/camera controlled, with capacity for timing and phasing revisions if required.
  • Intersection will include pedestrian crosswalks.
  • CONSTRUCTION START
    • Anticipated Construction start following bid and award is Spring, 2014.
  • CONSTRUCTION SEQUENCE
    • First phase of project work will involve movement/replacing of all utilities on and near the site. No detours and minimal traffic impacts are anticipated in this phase. In a later phase replacing the small bridge on Mill Road Eastbound may have an intermittent 24-hour detour for eastbound traffic only (see detail). The majority of the intersection construction will utilize both Mill Road Eastbound detour (during working hours only) and lane shifts with the assistance of flaggers and/or police.
  • LENGTH OF PROJECT: Overall length of project from start to finish is approximately 18-19 months.  Consisting of preparation work (up to 6 months) to accommodate the relocation of high power utility poles. The relocation of these poles will clear the way for the remaining construction improvements (up to 6-7 months).
  • DETOUR ROUTE: 

Striping Plan (Map of intersection)pdf

ASSOCIATED PROJECTS

Two other related transportation projects will be executed in conjunction with this project.  The replacement of the Maple Run Bridge on Mill Road in Egg Harbor Township and Northfield, and the replacement of the Cedar Bridge on Zion Road, in Egg Harbor Township, Northfield and Linwood will occur in conjunction with the Intersection Project. Each bridge is a critical alternate route within the detour plan for the other bridge and will therefore be replaced in tandem. Replacement of the Maple Run Bridge will occur first, within the construction period of the intersection.  

Sequence of construction associated with Fire/Mill Intersection, Maple Run Bridge Replacement, Cedar Bridge Replacement.

REPLACEMENT OF MAPLE RUN BRIDGE

  • CONSTRUCTION START:  March 3, 2014 (Concurrent with intersection project)
  • CONSTRUCTION SEQUENCE:
    • Move/Replace Utilities
    • Remove Bridge Structure, Demolish Footings
    • Replace Footings, Supports
    • Install/Construct New Bridge and Roadway Surface
    • Bridge will be demolished and replaced. Mill Road will be closed in vicinity of the bridge, as this work is underway.
  • LENGTH OF PROJECT: 3 Months
  • TRAFFIC CONTROL: Full Detour
  • DETOUR ROUTE: 

REPLACEMENT OF CEDAR BRIDGE

  • CONSTRUCTION START: Fall 2014 (Upon completion of Maple Run Bridge)
  • CONSTRUCTION SEQUENCE:
    • Move/Replace Utilities
    • Remove Bridge Structure, Demolish Footings
    • Replace Footings, Supports
    • Install/Construct New Bridge and Roadway Surface
    • Bridge will be demolished and replaced. Zion Road will be closed in vicinity of the bridge, as work is underway.
  • LENGTH OF PROJECT: 6 Months
  • TRAFFIC CONTROL: Full Detour
  • DETOUR ROUTE: